THE DEVELOPMENT
A power warning at a major AI campus and a new grid-upgrade program
Reuters reported on September 24 that Oracle sent a force-majeure notice to the Blue Owl unit developing Project Jupiter in New Mexico, citing potential difficulty securing power. The notice seeks contractual protection if specified events disrupt performance. Reuters’ source said Oracle is responsible for securing the site’s power.
The 1,400-acre campus has reportedly secured about $18 billion in loans and forms part of Oracle’s AI computing commitments to OpenAI. Reported obstacles include a natural-gas pipeline and permitting challenges. Oracle says the project remains on its planned 2028 schedule. Blue Owl says financial commitments are unchanged. The notice therefore does not establish a confirmed construction delay or cancellation.
Also on September 24, the U.S. Department of Energy announced plans to support 31 grid-improvement projects across 26 states. The proposed $5.25 billion total combines $1.9 billion in federal funding with $3.35 billion from recipients. The work includes replacing existing transmission wires with higher-capacity conductors and using technology to carry more electricity over existing lines.
DOE expects the projects to rebuild or upgrade more than 1,500 miles of lines and deploy grid-enhancing technology across nearly 21,000 miles, making more than 23 gigawatts of additional transmission capacity available. A gigawatt is 1,000 megawatts. These are expected future benefits, not completed capacity or a guarantee of power for any particular data center.
PREMIA VIEW
Power delivery needs its own evidence before fiber construction begins
Premia’s assessment is that a signed tenant and committed financing address only part of a fiber provider’s risk. A network built ahead of the electricity supply can sit unused, delaying revenue while capital remains tied up. Power generation, fuel supply, transmission access and permits therefore need separate review, even when the customer is a major technology company.
The DOE selections suggest an opportunity to examine locations served by existing transmission corridors scheduled for upgrades. Some may become more attractive than sites dependent on entirely new lines. That is a project-screening hypothesis, not evidence that any individual campus can open sooner. The useful comparison is the site’s verified power-delivery schedule before and after the upgrade.
DECISION QUESTIONS
Three questions stakeholders should answer now.
- 01What has to be finished before the first usable power arrives?
Confirm generation, fuel or pipeline access, grid connections, permits and commissioning. Identify the party responsible for each milestone and the evidence supporting its date.
- 02Who pays if the opening moves?
Review customer payment obligations, construction funding and delay provisions. Match fiber spending to documented progress and contractual protection.
- 03Which grid upgrades actually help this site?
Map the selected projects to the local utility and data-center connection. Verify funding, completion dates and whether additional capacity will be available to that customer.
WHAT TO WATCH
Project-level milestones will determine the commercial outcome
For Project Jupiter, watch updates on power supply, the pipeline, permits and the 2028 schedule. For the DOE program, watch funding agreements, utility implementation plans and individual completion dates. The department’s announcement does not provide a single date when all the additional capacity will become available.
Premia takeaway: confirm how and when electricity will reach the site, check that the required infrastructure is funded, and align fiber construction with the customer’s contractual commitments and readiness. Strong demand matters most when the site can turn it into paying traffic.
SOURCES
Reporting and primary materials.
- ReutersOracle triggers force majeure on data-center project over power delays, source says — September 24, 2026↗
- U.S. Department of EnergySpeed to Power investments across 26 states — September 24, 2026↗
Premia’s analysis reflects information available as of the publication date. Reported facts are attributed to the linked sources; the Premia View and decision questions are our analysis.